UPDATE 5/18: Lincoln Blvd. Milling and Resurfacing
UPDATE 10am May 18 | The Middlesex County Road Department will be paving Lincoln Blvd between Mountain Avenue and Cedar Avenue on Friday, May 19 and Monday 22 between 7 am–3 pm.
UPDATE 4pm May 10th | The County has informed us there will be a delay from the original projected start date. The contractor will now begin milling on Wednesday, May 17. 2023. Due to weather and equipment failures the milling/paving project will be delayed a few days.
The Middlesex County Department of Transportation’s Office of Public Works has advised the Borough that work is scheduled to begin on Lincoln Boulevard this week. The milling and resurfacing project is subject to availability of equipment and weather permitting. The anticipated schedule is shown below.
Project: Milling and Resurfacing Lincoln Blvd
Project Limits: Cedar Ave to Mountain Ave
Approximate time(s) 7:00 am to 3:30 pm (Mon-Fri only)
Activity – Start/End Date
Milling – Wed-Thu, May 17-18 May 11-12, 2023
Paving – TBD Wed-Thu, May 17-18, 2023
Striping – TBD Fri, May 19, 2023
Dates are Tentative (Subject to Change)
We regret any inconvenience that may result from this activity. Should you have any questions concerning this matter, please feel free to contact the County DOT, Office of Public Works, at 732-940-3800, www.middlesexcountynj.gov.